Screen-print style poster of a delivery calendar over an LNG terminal

CASE STUDIES / SCHEDULING · DEC 2​025

The wrong delivery months erase the margin.

Every feasible delivery schedule for a European DES short, evaluated against the forward curve. Month selection alone swings the programme from profit to a multi-million loss.

-$3.2M

WHAT THE WORST OF 56 FEASIBLE SCHEDULES LOSES · THE BEST EARNS +$0.84M ON THE SAME FOUR CARGOES

View as slides (PDF) →

One short, fifty-six ways to serve it.

01 · THE CONTRACT

A four-cargo DES short against spot DES cover, April to December 2026. One cargo is contractually locked into May, leaving three delivery months to choose from eight: exactly 56 feasible schedules. The first-best plan is easy to compute, but often not executable against business restrictions, so the deliverable is the full ranking of every plan, not a single answer.

FORWARD-CURVE EVALUATION · ADP = ANNUAL DELIVERY PROGRAMME · MONTE CARLO FLAGGED AS THE FOLLOW-UP STUDY

THE CONTRACT ON THE TABLE

DES Short · Europe (Gate)4 X 3.5M MMBTU · 125% HH + $5
DES Long cover · spot100% TTF - $0.20 · ALWAYS SOURCEABLE
May cargoPRE-LOCKED · ADVERSE SPREAD
HorizonAPR TO DEC 2​026 · ONE CARGO PER MONTH
Feasible schedulesC(8,3) = 56

The curve decides which months pay.

02 · THE SPREAD

The monthly spread between the short's HH-linked price and the TTF-linked cover is the whole game. July, August and December are the only months above water; the pre-locked May sits at roughly -$0.30 per MMBtu and drags every feasible schedule down with it.

-0.4-0.20+0.2+0.4APRMAYJUNJULAUGSEPOCTNOVDEC+0.10+0.11+0.32-0.30 · LOCKED INOPTIMAL MATCHES: JUL · AUG · DECMONTHLY SPREAD: DES SHORT (125% HH + $5) MINUS COVER (100% TTF - $0.20) · $/MMBTU
EXACT MONTHLY SPREADS FROM THE ENGINE: -0.44 / -0.30 / -0.12 / +0.10 / +0.11 / -0.03 / -0.07 / -0.07 / +0.32 $/MMBTU

Ten schedules, one thin margin.

03 · THE RANKING

The best plan, May-July-August-December, earns six cents per MMBtu. By rank ten the programme is already loss-making, and the average of all 56 schedules sits at minus nine cents: a swing of roughly $4M between best and worst on four cargoes.

00.020.040.060.060#1 · MAY JUL AUG DEC0.029#2 · MAY AUG SEP DEC0.025#3 · MAY JUL SEP DEC0.019#4 · MAY AUG OCT DEC0.018#5 · MAY AUG NOV DEC0.015#6 · MAY JUL OCT DEC0.014#7 · MAY JUL NOV DEC0.006#80.002#9-0.016#10DECEMBER SITS IN EVERY TOP-10 SCHEDULEFORWARD-CURVE PROFIT PER SCHEDULE · $/MMBTU · RANK 10 IS LOSS-MAKING
TOP 10 OF 56 FEASIBLE SCHEDULES · MEAN -0.09 · MEDIAN -0.08 · WORST -0.23 $/MMBTU (APR MAY JUN NOV)

Every constraint has a price tag.

04 · THE LEVERS

Re-running the same contract under different rules shows what each clause is worth. Freeing the May lock more than doubles the programme. Excluding December turns everything loss-making. Intra-month windows with shifted indexation weights unlock curve-shape premia, and an NBP-sourced cover nearly quadruples the base optimum through friendlier NBP-HH spreads.

00.10.20.06BASE · MAY LOCKED0.125NO MAY LOCK-0.03MAY LOCKED + DEC EXCLUDED0.08INTRA-MONTH WINDOWS0.23NBP-SOURCED COVERBEST FEASIBLE SCHEDULE PER REGIME · $/MMBTU · SAME CONTRACT, SAME FORWARDS
EXACT: MAY LOCKED $0.84M TOTAL · UNRESTRICTED $1.75M (+108%, 56 → 126 SCHEDULES) · INTRA-MONTH 4,536 SCHEDULES · NBP RE-RANKED

05 · THE VERDICT

A DES programme lives on six cents per MMBtu:
and one pre-locked month can push the whole book into loss.

Time-window selection is a primary P&L lever, not an operational afterthought. Whoever ranks every feasible schedule knows the price of each concession before the negotiation starts.

What the 56 schedules teach.

06 · TAKEAWAYS

The full ranking beats the first-best

The top schedule is easy to find, but it is often not executable against counterparty demands. Ranking all 56 plans shows what each concession costs: by rank ten the programme is already loss-making.

Single months are worth millions

Freeing the pre-locked May cargo lifts the best plan from $0.84M to $1.75M, a 108% uplift. Excluding December, which sits in every top-10 schedule, turns ALL remaining feasible plans loss-making. Every calendar concession has a price tag.

!

This is the forward-curve lens only

Margins are thin, the mean schedule loses nine cents per MMBtu, and the curve moves daily; rankings must be refreshed. A stochastic Monte Carlo treatment of window risk is flagged as the follow-up study.

Modelled with X-LNG.

07 · THE TOOL

1

Your world goes in

Contracts, vessels, charter rates, prices, spot assumptions and constraints. The full book, not a slice.

2

One optimal plan comes out

Feasible, P&L-maximising and constraint-compliant, re-solved for every scenario in minutes.

3

Every number checks out

Each result can be recalculated by hand. Transparency your risk committee can audit.

CLOUD-BASED, ANY PORTFOLIO SIZE · BUILT AND ADVANCED DAILY BY ~25 MATHEMATICIANS, PHYSICISTS AND COMPUTER SCIENTISTS